![]() |
|
| if you can see this your browser doesn't understand the menu system. Please click here for a pop-up menu. |
The Story of the New SGC Hangar
SGU Hangar Project – Status at 7th November 2004
The club fleet is in. The private fleet is in. Lots of gliders have been moved in and out lots of times Everything seems to work ok. A few months behind schedule but we're there! There are some photographs of the project on this website and Kevin Hook has lots more.
new_hangar_photos_1.htm
new_hangar_photos_2.htm
new_hangar_photos_3.htm
SGU Hangar Project – Status at 19th October 2004

At last
the expected good news. The doors have arrived and been fitted.
With luck, we will transfer the club fleet to the new hangar over the weekend.
Regards,
Kevin
SGU Hangar Project – Status at 20th September 2004
Following a visit to D W Thomson's premises last week , we are pleased to report that 50% of our hangar doors appear to be complete and awaiting
delivery. There is still some work to be completed on site
prior to door installation, but it seems likely that we will see doors being
installed around the turn of the month.
Whilst the delay to the project has been embarrassing and inconvenient, it has
given us the opportunity to complete our own internal fit out and wiring work
with both good access and more than adequate natural lighting. This time has
also been used to complete other important self help tasks such as laying paving
slabs and reinstating the ground around the building. We have also had our
drainage and fire water reservoir installed by Meiklem Drainage during this
period. We are very pleased with the results we have achieved with electrical
fit out, wheel guides and wing supports.
We are looking forward to installing the club fleet in the hangar in early
October, and trust that we will not have too much difficulty persuading the
building inspector to issue a completion certificate.
To all those who have helped with the recent phases of the project, please
accept our most sincere thanks. In particular, the club owes a great debt to
former member, Kenny George who has put an immense amount of effort into
designing and overseeing the electrical installation within the building.
Undoubtedly, we will encounter unforeseen difficulties as we commence full use
of the building, and we hope that all members will bear with us and offer their
assistance to help iron out the teething problems.
Kevin Hook
John Williams
SGU Hangar Project – Status at 22nd April 2004
Steel fabrication and galvanising completed at the end of March, delivered on site on April 8th and erection completed only 1 week later. Steelwork photographs here.
SGU Hangar Project – Status at 10th December 2003
Due to an unexpectedly mild spell of weather at the beginning of December all of the groundworks for the new hangar have been completed unexpectedly quickly and ahead of schedule. Because of the long dry spells of weather lasting throughout the Summer and Autumn the South Field turned out to be much drier
than usual and this too helped progress. Much of the work has been done by club members with professional supervision and assistance to help with the setting out and machinery operation. At the end of only 1 week the foundations and concrete pads for the steelwork have been laid, the floor membrane installed and a layer of ballast spread over it. See the hangar photograph gallery for some views of the works in progress. The steel is not scheduled for delivery until Spring and so work will now come to a halt for the winter.
Architects drawings of the hangar are on display in the clubhouse lobby opposite the noticeboard together with artist's impressions of the various aircraft in their allocated positions. Plans of the South Field show the final positioning of the hangar and the (relatively small) impact which it will have on the runway area.
SGU Hangar Project – Status at 28th September 2003
As you are aware the new hangar project was delayed because the initial quotations for the work were greater than anticipated.
We have now obtained a quotation from another contractor, applied some reduction to the original specification and now plan to carry out some of the basic ground works ourselves, under professional supervision. With a small additional investment from the private owners, this brings the estimated costs to the SGU close to the originally budgeted figures.
Your board has therefore decided to proceed with this project to provide you with much safer aircraft accommodation, improved access to our fleet, modern hangarage and an opportunity for integrated redevelopment of our main building complex in the future.
This is being achieved without prejudice to the programme of replacement of capital assets which will shortly be outlined in our 10 year forward plan.
A contract for the steelwork will be let very shortly. Ground works will commence within the next few weeks, and erection of steel on site will begin at the beginning of April 2004. In order to provide access to the works, owners of trailers will be contacted shortly and advised where trailers can be parked during the works. On completion, it is intended to reinstate the trailer park with improved access and ground conditions. This will allow access for the grass cutters to keep the trailer park tidy in future.
Clearly this project will benefit from the full cooperation and support of the entire membership to bring it to a successful completion.
Remember, this is your club and it will be what we make it together.
signed
B.M.Cole-Hamilton
For your board of directors
28th September 2003
SGU Hangar Project – Status as at 30th May 2003
Background.
The project, with support from the Board and with up-front cash from many private owners/syndicates has now received a number of tenders for construction. The tenders have shown costs greatly exceeding those budgeted, particularly for the groundworks element. The Board still hopes to be able to proceed with the project by finding cost savings and/or additional funding, but is firmly opposed to major borrowing. Planning permission and a building warrant have now been successfully obtained.
On 23rd May, a meeting was held with all those who had put up cash in anticipation of a promptly built hangar.
Emerging Views
After considerable discussion the following broad views emerged:-
Proposed Club Requirements
What does this mean?
A revised specification to meet these requirements is currently being priced by a new contractor who has extensive experience of hangar construction. The revised drawings may well require to be re-submitted for planning and building control. It is unlikely that we will be in a position to start construction in less than 3 months time, and quite possible that we will not be able to start until next spring.
KDH, BCH, JDW, 07/06/03
| page last updated on 7th
November 2004 ©2003-2004 and the |
click here to open a separate menu window |